Lighthouse Dune | September 2026 Construction Update

Traders In Purple is pleased to share the latest developments for Lighthouse Dune.

Throughout September, construction continued to progress well across site with in-ground services and the final ground floor slab works nearing completion. The first suspended slab pour to Level 2 has been completed, with further pours underway. Vertical structural works have also progressed to Level 2, alongside the ongoing installation of precast elements.

Looking ahead to October, focus is on completing the final ground floor slab pour, continuation of Level 2 suspended slabs and vertical structural works as the building rises.

We look forward to bringing you more updates next month as construction continues on Lighthouse Dune.